Re: Stadium Site pictures : Thu Jan 05, 2012 6:19 pm
zinser wrote:
well said saints fan. (we dont usually agree do we) Dont want to have to try and explain design and build, but its not the contractor who designs, the contractor does what it says on the plans, believe me, if anyone from the builders thought for one second it was the contractors fault they would be shouting it from the (damaged rooftop). there will be people now working out calculations to stop this happening again. Then we can move on, ill bet there has not been one building site ever without problems, its just one of those things, but our stadium is in the spotlight so everything is blown out of proportion
Clearly you are an expert in this, but what you are saying, and what the contractor is saying are two completely different things. Are you saying that the contractor lied in this article, because it is pretty clear to me that they are claiming the credit on numerous occasions for designing the roof as well? Maybe you could take some time to explain design and build, because it is pretty confusing to a mere pleb like me.
CSP Roofing designed and installed the roof of St Helens’ new £20m Langtree Park ground. The 18,000-seat stadium is due to open in time for the new Super League season which kicks off next January.
Contracts director Keith Hope said: “This was a very important contract for us.
“It took a lot of design work and there was immense pressure to get it completed on time, which we did.
“It took some getting because the design work involved was pretty intensive. I think that’s why we shone through and won the work; because we were able to come up with answers.