redeverready wrote:
The riverside stadium which was built in no mans land only took 32 weeks to complete. Even the bigger Ashburton Grove (Emirates) was completed in 18 months.
We are talking about moving probably approaching a million tonnes of earth and hardcore into the hole to fill it (dense earth weighs about 2t per m3, there will be a lot of heavier hardcore involved, and we were told 350k m3 was needed so do the maths. Something that was not necessary at those other sites. There are also issues of piling and the like given the generally unstable nature of the site (old tip and all that). That is before any basic groundworks can begin.
How many tons on a big wagon? We were told anyway it was at least 200 trucks a day for 6 months if it all had to be trucked in from offsite. At 30t/wagon thats around a million tons anyway.
And none of this was required at other stadium sites - this one is unique.
For that reason, I'm happy to take the good counsel of Cibaman's mate.